A gangway with a hinged or sliding connection is a common way to connect an existing fixed pier to a modular floating dock. Before choosing the layout, check where the existing structure can carry the gangway reaction, where the floating end will land at high and low water, and how the dock will be held in position.

Aerial view of gangways between a fixed shoreline and floating docks
Hisea Dock project. Several gangways connect a fixed shoreline to a floating dock system.

Where can the gangway land on the existing pier?

Mark the proposed opening and gangway centerline on the existing drawings. A flat concrete surface may be a structural slab, a seawall cap, or a wearing surface over another structure. Ask the project engineer to identify the member that can take the gangway reaction and check the proposed connection and the existing structure.

Use one elevation datum for the fixed landing, highest and lowest operating water levels, and any survey levels. Record the location and water level for each depth measurement. On the plan, mark steps, wall corners, protruding piles and vessel clearance so the designer can compare a straight approach with an angled one.

Angled metal gangway connecting a fixed shore to a blue and orange modular dock
This angled approach runs from the shore to a modular floating platform. Mark the shore opening, mounting location and dock-side entry on the site plan.
Blue modular dock running alongside a concrete seawall
Along a seawall, measure the narrowest clearance and locate anything that protrudes into it.
View from a grey modular dock toward the gangway and stone shoreline
A view toward shore helps check the approach against the existing path.

How much does the same gangway move as water levels change?

Estimate the floating deck elevation by adding loaded freeboard to the water elevation for each condition. As the gangway pivots, its horizontal run changes with its slope. Check both ends of the operating range and consider a reverse slope if the floating deck can rise above the fixed landing.

Side section showing a fixed hinge, two floating deck elevations and sliding travel at the dock end
Two operating conditions share the same fixed hinge. The deck sits above the water. The illustrated dock-end travel is exaggerated for clarity.

Example with a 6.00 m gangway. The distance between the supports is 6.00 m and the fixed landing is at +3.00 m. For each condition, divide the elevation difference by the corresponding horizontal run and multiply by 100 to get the slope.

ConditionDock deck elevationElevation differenceHorizontal runSlope
High water+2.75 m0.25 m5.995 m4.2%
Low water+1.75 m1.25 m5.868 m21.3%

The horizontal run changes by about 0.13 m in this example. That is the geometric change from the gangway pivoting. The project designer also needs to allow for dock movement and installation tolerances when sizing the bearing area. Check the applicable slope, transition plate and accessibility requirements for the site and its intended use.

U.S. Access Board guidance on recreational boating facilities

Leave a bearing area for the moving end

A common arrangement pairs a fixed-end hinge with rollers or sliding support at the dock end. Ask the designer to show the moving end’s full operating range. Check minimum bearing overlap, gaps and changes in level at the transition plate, and clearance from railing posts or other hardware. The gangway concentrates its reaction near the bearing area. Review the support, local freeboard and deck tilt under the design loads.

Metal gangway meeting the walking surface of a dark floating dock
Show the transition plate, bearing area and maintenance access on the same detail drawing.
Steel gangway framing visible before the walking surface is installed
Inspect support and fastener positions before decking hides them.
Yellow strip at the walking transition and rails on both sides
Check gaps, steps and the railing opening in the direction people will walk.
White gangway meeting a wider blue and orange modular platform
Set the entry area and nearby railing post positions together.

Docks, Piers and Wharves, New York Sea Grant design guide hosted by NOAA

Check dock restraint and gangway movement together

Guide piles, shore restraints and moorings are options for holding a floating dock in position. The choice depends on depth, bed conditions, the shore structure and environmental loads. For guide piles, verify working travel across the operating water levels. Along a wall, check lateral clearance, fenders and protrusions.

Overlay the possible dock positions on the gangway plan. Where currents or vessel wakes can move the dock, check whether the end support remains on its bearing surface as the dock shifts or turns. The designer should also verify any additional lateral forces at the gangway connections.

White pile beside a floating walkway and a visible adjacent fitting
Identify where the guide hardware needs to travel along the pile.
Floating dock with blue floats, piles and fenders along the edge
Check the restraint hardware and the clear space needed for berthing.
Wide view of a modular dock running along a sloped shoreline
Mark the dock perimeter, construction access and shore-side clearance.

U.S. Army Corps of Engineers guide pile detail example · Hisea Dock’s guide to anchoring a floating bridge across changing water levels

What to send with a retrofit quote request

Send to the supplier and designer

  1. Existing pier plan, proposed connection location, close-up photos and available structural drawings.
  2. Fixed-end elevation, operating water levels and surveyed depths tied to the same datum.
  3. Clear walking width, expected traffic, cart or equipment access, accessibility requirements and construction constraints.

Check the drawings and scope

  • High and low water sections showing slope and dock-end position.
  • Details of the fixed connection, floating-end support and restraint.
  • Supply and installation responsibilities for the gangway, mounting seat, transition plates and restraints.

To reuse an existing gangway, provide its measured length, clear width, connection details and maintenance records. Have the designer verify that it can accommodate the new support positions and range of movement.

Side view showing a gangway spanning from shore to a floating dock
Include a side view that shows the relative elevations at the two ends.
View along a metal gangway toward the grey modular dock
Include a view along the approach to show clear width and turning space.

Project photographs are from the Hisea Dock case archive and include modular float and pontoon installations. The section and dimensions illustrate the calculation.

Table of Contents

    Contact us now!

    Share

    Share

    Leave a Reply

    Your email address will not be published. Required fields are marked *

    Customize a Floating Dock that Works Best for You.

    Contact Us